Overview
Challenge
The facility could not close, and staff worked directly beneath the work area. The roof was weathered but structurally sound, so a full tear-off would have created cost and disruption the building did not need.
Approach
We proved the deck and insulation were dry before recommending restoration, then built a phased plan around shift patterns, deliveries, and access points so no work zone ever sat above an active area.
Execution
Work moved in defined phases with protected access routes and daily site resets. Seam work and targeted repairs came first, followed by a reflective coating system applied in weather windows agreed with the facility manager.
Scope of Work
Moisture survey and deck verification
Seam repair and flashing remediation
Reflective coating system application
Phased access planning around operations
Outcome
The client extended roof life without a tear-off, avoided the cost of full replacement, and kept the facility running every day the crews were on site.
Building Type
Occupied Facility
Roof System
Coating Restoration
Duration
4 Weeks