Del Rio, TX
Explore Project

Large-Scale
Delivery
Roof Replacement
Service
Schedule Protected
Focus
2025
Year
Overview
Challenge
The existing system had failed across a large footprint and the owner had a fixed date driven by an incoming tenant. Weather exposure during tear-off was the single largest risk to the programme.
Approach
We divided the roof into daily dry-in targets so no more area was ever opened than could be closed the same day, and staged materials in advance to remove supply delays from the critical path.
Execution
Tear-off, deck repair, insulation, and membrane followed each other section by section. Debris was removed daily, perimeter protection stayed in place throughout, and progress was measured against dry-in targets rather than square footage alone.
Scope of Work
Sectional tear-off with daily dry-in targets
Deck repair and fastener replacement
Insulation upgrade and new membrane install
Safety perimeter and daily debris removal
Outcome
The building was handed over on the tenant deadline with no weather-related damage during construction and a full manufacturer warranty in place.
Building Type
Industrial Facility
Roof System
Full Replacement
Duration
10 Weeks